I-805 HOV/Managed Lanes-South (Palomar to SR54)

Description: I-805 HOV/Managed Lanes-South (Palomar to SR54)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Chula Vista, National City
Zip Code
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
 
County/State Route San Diego 805
Postmile Begin/End 5.5 9.4
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (HOV)      3.9  
Lane Miles Added (Mixed)  3.9      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Ramon Martinez (619)688-2516   Ramon.Martinez@dot.ca.gov
Design (PS&E) Phase
Caltrans Ramon Martinez (619)688-2516   Ramon.Martinez@dot.ca.gov
Right of Way Phase
Caltrans Ramon Martinez (619)688-2516   Ramon.Martinez@dot.ca.gov
Construction Phase
Caltrans Ramon Martinez (619)688-2516   Ramon.Martinez@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$62,053 $-24,075 $37,978
Non-bond Funding
State/Federal*
$244 $0 $244
Local**
$22,818 $-5,608 $17,210
 
Total**** $85,115 $-29,683 $55,432

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$7,754 $0 $7,754 $3,933
Design(PS&E)
$6,000 $0 $6,000 $4,709
Right of Way
$0 $0 $0 $0
Construction
$71,361 $-29,683 $41,678 $43,631
 
Total* $85,115 $-29,683 $55,432 $52,273

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/30/2007 

06/22/2011 
 

 
05/30/2007 

06/22/2011 
100  05/30/2007 

06/22/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/09/2009 

12/30/2011 
 

 
12/09/2009 

12/30/2011 
100  12/09/2009 

12/13/2011 


Begin Right of Way Phase

End Right of Way Phase
 

11/28/2012 
 

 
 

11/28/2012 
100   

11/21/2012 


Begin Construction Phase

End Construction Phase
04/30/2012 

07/30/2014 
 

 
04/30/2012 

07/30/2014 
100  04/27/2012 

04/03/2014 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
04/01/2017 

11/01/2017 


Corridor System Management Plan
Adoption Date 08/09/2010    08/09/2010  08/09/2010 
Implementation Date 08/09/2010    08/09/2010  08/09/2010 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (HOV) 3.9
Lane Miles Added (Mixed) 3.9

Bond Funding Cost
Adopted:
$62,053,000
Current Approved:
$37,978,000
Actual Expenditures:
$37,978,000

 

Status as of December 31, 2023.